Remacor, Inc.

All POLREP's for this site Remacor, Inc.
West Pittsburg, PA - EPA Region III
POLREP #90 - Sampling Media
Printer Friendly  |   PDF
 
On-Scene Coordinator - Jack Downie 12/5/2007
Emergency - Removal Action Pollution Report (POLREP) #90
Start Date: 9/15/2006
Pollution Report (POLREP) #90
Site Description
EPA is continuing emergency removal actions at this site during the repackaging, transportation, and removal of flammable magnesium materials.  Magnesium generators, who previously supplied Remacor with recyclable magnesium and magnesium alloys, are removing their materials from the site.  Intermet is presently removing its material off site.  Winters Performance Products, Inc. has completed packaging and is presently shipping material off site.  MJ Metals of Bridgeport, CT, has completed repackaging its material and is presently shipping material off site.  SPX Contech will be repackaging its material in preparation to ship it off site.  

EPA’s ERRS contractor Guardian Environmental Services, Inc. (GES) is continuing to  work burn piles and react material in the reaction pit.  Before reacting the material in the reaction pit GES has to empty drums from the piles which may contain material that may not have been reacted.    PADEP is providing technical and oversight support at the site.  EPA START contractor TechLaw is providing technical and administrative support to EPA as well as doing a full site assessment.  EPA and PADEP officials continue to control access to the site in addition to coordinating the activities of the various generators.  


Current Activities
Personnel On-Scene:
12/04/07 EPA-3, PADEP-1, START-3, Dade Moeller-1, ERRS-10, MHF-1, Other-3, Security-1 (24 hr)
12/05/07 EPA-2, PADEP-1, START-3, Dade Moeller-1, ERRS-10, MHF-2, Security-1 (24 hr)

Weather:
12/04/07 Low of 23° F, high of 25° F.  Light Snow, 0.00 inches of precipitation, wind WNW 7-13 mph.
12/05/07 Low of 19° F, high of 25° F.  Light Snow, 0.00 inches of precipitation,  wind N 6-10 mph.

12/04/07
START attended Morning safety meeting held by MHF a contractor for multiple PRPs’.  MHF was on site to ship 1 load for Intermet and to over-pack drums for SPX Contech.   The Intermet load consisted of 96 drums (4 drums/pallet) with an estimated weight of 42,500 pounds, it was transported by Hazmat Environmental, Buffalo, NY with the receiving facility being MagRetech, Bellevue, OH.

EPA’s OSC Jack Downie was on site for oversight and site control.  EPA’s Senior Site Administrative Officer Rich Messimer was on site for administrative oversight.  EPA’s Rich Messimer demobilized.

U.S.EPA’s Environmental Response Team Member Greg Powell and EPA contractor from Dade Moeller & Associate Douglas Draper were on site to help START characterize the RAD samples and high RAD material that need to be sampled.

START attended morning safety meeting held by EPA, ERRS contractor Guardian Environmental Services, Inc.  ERRS continues to work on burn piles 9 and 10.  ERRS has removed approximately 85 drums of various conditions from the burn piles.  ERRS will continue to sift materials from the burn piles and separate large debris and metals so that the sifted material can be reacted in the reaction pit.

Neither the Data Rams nor the PDR were run due to inclement weather.  
  
START continued with screening using the InnovX-1000 and collecting soil samples.  START collects soil samples in inclement weather because the InnovX-1000 is not effective in damp areas.   START continues to assist the EPA as needed, conduct written/photographic documentation, and monitor activities conducted on site.  

12/05/03
START attended Morning safety meeting held by MHF a contractor for multiple PRPs’.  MHF was on site to ship 2 loads of material and finish over-packing drums for SPX Contech.   One load was shipped for Intermet it consisted of 76 drums (4 drums/pallet) with an estimated weight of 35,000 pounds, it was transported by Hazmat Environmental, Buffalo, NY with the receiving facility being MagRetech, Bellevue, OH.  The other load was shipped for MJ Metals and consisted of 128 drums (4 drums/pallet) with an estimated weight of 38,000 pounds and was transported by Speed Global, Buffalo, NY and consigned to Speed Global, Buffalo, NY.

EPA’s OSC Jack Downie was on site for oversight and site control.  

U.S.EPA’s Environmental Response Team Member Greg Powell and EPA contractor from Dade Moeller & Associate Douglas Draper continued to assist START in characterization of RAD samples and high RAD material that need to be sampled.  Greg Powell and Douglas Draper demobilized.

START attended morning safety meeting held by EPA, ERRS contractor Guardian Environmental Services, Inc.  ERRS continues to work on burn piles 9 and 10.  ERRS has removed approximately 95 drums of various conditions from the burn piles.  ERRS will continue to sift materials from the burn piles and separate large debris and metals so that the sifted material can be reacted in the reaction pit.

Neither the Data Rams nor the PDR were run due to inclement weather.  
  
START continues to screen using the InnovX-1000 by collecting soil samples.  START collects soil samples in inclement weather because the InnovX-1000 is not effective in damp areas.   START continues to assist the EPA as needed, conduct written/photographic documentation, and monitor activities conducted on site.  



Next Steps
Intermet suspended all shipping of its material because of ice on the drums they will resume shipments the week of 12/10/07.

Winter Performance Products, Inc’s plans to continue shipping its material off site until all material is removed.

SPX Contech has a tentative schedule to begin shipping material the week of 12/10/07.

MJ Metals (generator) plans to ship its last load off site by 12/11/07.  

EPA START contractor TechLaw, Inc. plans to finish al sampling by 12/09/07.

EPA will continue to coordinate with magnesium waste generators for the safe and appropriate removal of the material from the site.  EPA will continue to coordinate with all local, state, and federal agencies.


Key Issues
The fire debris piles remaining on slab #3 that constitute the remains of a 68,000 square foot building that was destroyed during the Remacor fire on August 6, 2005 continue to be worked on. The piled fire debris contains construction material intermixed with charred, damaged and deteriorated drums containing reactive magnesium fines and oxides and other process alloys or materials.  The nature of the reactive materials mixed with building debris requires careful handling and segregation while increasing the risk of a fire due to exposing once-buried materials to the elements.  EPA has been in the process of slowly segregating and processing the remaining fire debris piles. The magnesium-based oxides and fines that are segregated from oversized building debris are being managed on site in order to make them safer to handle. EPA is coodinating with the West Pittsburg Fire Chief in regards to these high hazard operations.  

 
Disposition Of Wastes
Disposal Summary as of 12/05/07

Magnesium Turnings, Flammable Solid, Haz Mat: 3,881,960 pounds
Magnesium Scrap, Non-Haz Mat: 766,273 pounds
Total: 4,648,233 pounds