Remacor, Inc.

All POLREP's for this site Remacor, Inc.
West Pittsburg, PA - EPA Region III
POLREP #145 - Removal Action
Printer Friendly  |   PDF
 
On-Scene Coordinator - Jack Downie 5/28/2008
Emergency - Removal Action Pollution Report (POLREP) #145
Start Date: 9/15/2006
Pollution Report (POLREP) #145
Site Description
EPA is continuing emergency removal actions at this site during the repackaging, transportation, and removal of flammable magnesium materials.  Magnesium generators, who previously supplied Remacor with recyclable magnesium and magnesium alloys, are removing their materials from the site.  SPX Contech has been on site and identified the remainder of its material and is preparing drums to be shipped off site.  Intermet is re –working pallets and drums and is actively shipping material off site.  

EPA’s ERRS is repackaging material in Building #2 to make it DOT shippable and reacting material from Building #2 and Building #9.  PADEP is providing technical and oversight support at the site. EPA START contractor TechLaw is providing technical and administrative support to the EPA.  EPA and PADEP officials continue to control access to the site in addition to coordinating the activities of the various generators.  


Current Activities
Personnel On-Scene:
05/27/08 START-1, MHF-3, ERRS-1, Other-1, Security-1 (24 hr)
05/28/08 EPA-1, PADEP-1, START-1, MHF-3, ERRS-7, Other-2, Security-1 (24 hr)

Weather:
05/27/08 Low of 55° F, high of 70° F.  Overcast, 0.00inches of precipitation, wind WSW 5-13 mph.
05/28/08 Low of 39° F, high of 65° F.  Clear, 0.00inches of precipitation,  NNE 5-10 mph.

05/27/08
START attended the morning safety meeting held by MHF Logistics who is contracting for intermet, SPX Contech, and Product Technology.  MHF continued to change lids and pallets on SPX Contech material. MHF overpacked magnesium material belonging to Intermet into 85-gallon polyurethane drums.  

START mobilized to site assisted as needed and conducted written/photographic documentation.    

05/28/08
START attended the morning safety meeting held by MHF who is contracting for Intermet, SPX Contech, and Product Technology.  MHF resumed shipment of Intermet material.  MHF shipped 2 truckloads of Intermet material which consisted of 26 pallets @ 4 drums per pallet and 11 pallets @ 8 drums per pallet and had a combined weight of 80,480 pounds.  The loads were consigned to Speedway Global Services Buffalo, NY and were transported by Hazmat Environmental Buffalo, NY.

USEPA OSC Jack Downie mobilized to site for oversight of activities.  OSC Downie demobilized.

PADEP Mariruth Hoffman mobilized to site and assisted the EPA in oversight of activities.  PADEP Hoffman demobilized.

Emergency and Rapid Response Services (ERRS) contractor Guardian Environmental, Inc held its morning safety meeting and discussed the days planned activities. ERRS added material from Building #9 into the reaction pit in order to neutralize it for future shipment off site. To date ERRS has reacted the contents of 2,046 drums of residual waste material.

START assisted the EPA as needed and conducted written/photographic documentation.        



Next Steps
SPX Contech has changed its plans to ship the remainder of its material in the near future.

Intermet has plans to continue to ship material off site until they have completed shipping all their material.


EPA will continue to coordinate with magnesium waste generators for the safe and appropriate removal of the material from the site.  EPA will continue to coordinate with all local, state, and federal agencies.


Key Issues
None

 
Disposition Of Wastes
Disposal Summary as of 05/28/08

Magnesium Turnings, Flammable Solid, Haz Mat:4,332,931 pounds
Magnesium Scrap, Non-Haz Mat:766,273 pounds
Total:5,099,204 pounds
Low Level RAD drums:280,000 Pounds
Calcium Aluminum Drums:4,500 pounds